If you are not happy with the results, please do another search

Sidharth Sethi | Conference on Redefining ADR: New Opportunities for Justice and Innovation

Our Partner, Sidharth Sethi, was invited as a speaker at the National ODR Day Conference on Redefining ADR: New Opportunities for Justice and Innovation, organized by the Indian Institute of Arbitration & Mediation (IIAM) on 1 December 2024 at New Delhi.

The keynote address was delivered by Hon’ble Mr. Justice Surya Kant, Judge, Supreme Court of India.

Sidharth spoke on the topic, “Streamlining Arbitration: Reforms for Enhancing Efficiency and Effectiveness”.

The session was chaired by Hon’ble Mr. Justice K.V. Viswanathan, Judge, Supreme Court of India and moderated by Ms. Iram Majid, Advocate & Director, IIAM. The other esteemed panellists included:

  • Mr. Tejas Karia, Partner and Head of Arbitration, Shardul Amarchand Mangaldas;
  • Dr. Amit George, Advocate, High Court of Delhi; and
  • Mr. Mohit Dubey, IES, ACIArb, Deputy Director (MES), Ministry of Defence, Government of India.

 

Also present on the occasion was Dr. Rajiv Mani, Secretary, Ministry of Law and Justice.

‘Clean Slate’ Principle Upheld: Amounts awarded in arbitration must be claimed in CIRP of the award debtor – Madras High Court

JSA successfully represented Karaikal Port Private Limited (“KPPL”) before the Madras High Court, in a challenge to an arbitral award dated 17.2.2021. The arbitration was initiated by Coastal Consolidated Structures Private Limited (“CCSPL”) against Marg Limited (“Marg”) and KPPL. The parties had executed a tripartite agreement (“TPA”) in which KPPL had undertaken to discharge certain liabilities of Marg arising under a sub-contract between KPPL and CCSPL. In the arbitration, CCSPL had made separate claims against KPPL and Marg. The award held KPPL liable for a portion of the amounts claimed. All three parties challenged the award before the Madras High Court.

During the pendency of the challenge before the High Court, an order came to be passed by the National Company Law Tribunal (“NCLT”) commencing corporate insolvency resolution process (“CIRP”) of KPPL and appointed a resolution professional (“RP”) in terms of the Insolvency and Bankruptcy Code, 2016 (“IBC”). CCSPL did not submit any claim to the RP based on the award. The resolution plan of Adani Ports and SEZ Limited came to be approved by the committee of creditors and NCLT.

On resumption of proceedings before the High Court after conclusion of the CIRP, it was contended on behalf of KPPL that CCSPL by not submitting its claim to the RP had forfeited its right to enforce the award against KPPL. Reliance was placed on the judgement of the Supreme Court in Ghanashyam Mishra and Sons Private Limited v. Edelweiss Asset Reconstruction Company Limited, and other judgements, in support of the contention that failure to submit claim during CIRP will disentitle a party from pursuing the claim once a resolution plan is approved.

The Madras High Court by its judgement dated 14.10.2024 upheld the above contentions of KPPL and held that CCSPL cannot enforce the award against KPPL.

This judgement reinforces that once a resolution plan under the IBC is approved, any prior or pending claims against the debtor that are not part of the information memorandum are extinguished, giving the resolution applicant a “clean slate“. This judgement is particularly significant in the context of arbitral proceedings and enforceability of an award, as it deals with the interplay between the law of arbitration and the IBC.

Vinod Kumar, Partner, argued the matter for KPPL and was assisted by Saibarath, Senior Associate.

JSA successfully represented Tata Power’s Mundra Ultra Mega Power Plant (4150 MW) before APTEL to secure Change in Law compensation for impact on capital

In the saga of evolving regulatory jurisprudence on restitution for change in law, Judgment dated 25.10.2024 by Appellate Tribunal for Electricity (“Hon’ble APTEL”) partly allowing Tata Power’s claims for increase in capital cost during construction period has added a nuance to bid disclaimers and contractual obligations. Tata’s claims included expenses incurred in obtaining additional land for the project. The Judgment characterised Change in Law mechanism as contractual risk allocation amongst parties to a contract. Hon’ble APTEL allowed the claim holding that water intake system is essential for operations of a thermal plant, while rejecting the Procurers’ objections that:

  • Change in Law compensation must be limited to increase in cost of land identified in the PPA.
  • Disclaimers in the RFP and/or the PPA mean that representation of the Procurers including on land requirement etc. cannot be relied upon by the bidders who assume complete risk on such aspects.
  • Since land for the water intake and outfall systems was not part of the identified land as per the PPA, no compensation can be claimed for procuring land required for the same.

Hon’ble APTEL found that the judgement of Hon’ble Supreme Court in Haryana Power Purchase Centre vs. Sasan Power Limited & Ors. [2024 1 SCC 247] was not attracted due to difference in facts to hold that the bidder/generator is entitled to Change in Law compensation.

Hon’ble APTEL also allowed claims qua compensation for increase in rate of service tax on works contract; additional conditions imposed by Ministry of Environment, Forests and Climate Change, Govt. of India; and carrying cost.

Hon’ble APTEL rejected Procurers’ claims for expenses incurred for R&R since the same was found to have not been claimed/raised in the original proceedings before CERC or the Tribunal. It also rejected Tata Power’s claim for expenses incurred for excise duty re. procurement of civil material (steel and cement) for construction, and stamp duty for indenture of mortgage on the ground that the law existing prior to cut off date did not provide for exemption.

Mr. Amit Kapur argued the matter on behalf of Tata Power, assisted by Mr. Abhishek Munot, Mr. Malcolm Desai and Mr. Samikrith Rao.

JSA successfully represented Amplus Sun Solutions to secure a remand for redetermination of Capex with a sustainable interim tariff

JSA successfully represented Amplus Sun Solutions Pvt. Ltd. (“Amplus”) against Haryana Power Purchase Center (“HPPC”) in cross-appeals challenging HERC’s Order dated 18.01.2021 slashing by 36% Amplus’s fixed charges claims from Rs. 3.86 per kWh to a project specific levelized tariff of Rs. 2.48 per kWh.

The matter relates to determination of tariff in respect of Amplus’s 50 MW Solar Power Project in the State of Haryana at Bhiwani. Amplus’s grievance was that HERC had: –

  • Disallowed module cost and cost of civil works of Rs. 44 Crores and Rs. 6.81 Crores respectively relatable to the extra 25 MW Direct Current (“DC”) capacity [the plant was operating on 50 MW Alternate Current (“AC”) : 75 MW DC capacity], contrary to accepted industry practice where generators optimize installed AC capacity by installing Solar Panels of higher DC Capacity without exceeding the contracted capacity.
  • Allowed Interest on Term Loan and Working Capital @ 9% instead of actual 9.91%.
  • Erred to disallow IDC of Rs. 9.59 Crores on the wrong premise that Amplus has not borrowed funds.
  • HERC benchmarked O&M Expenses against BHEL’s quotes for 50 MW Solar Power Plant of NTPC in Andhra Pradesh.
  • Disallowed Project Management Expenses of Rs. 23.75 Crores without prudence check.

 

Per contra, HPPC challenged Impugned Order since: –

  • Capital Cost allowed is higher than other Solar Projects
  • CUF of 25.91% allowed instead of 27.17% as per generation data in Amplus’ PPA.
  • Degradation of 0.5% in CUF has not been allowed by other SERCs.
  • Escalation rate of 5.72% p.a. allowed for O&M Expenses should be reduced.

 

Amplus had sought pro-tem tariff of Rs. 3.03/ kWh, inter alia, since: –

  • Amplus was prevented from drawing down the balance term loan facilities due to the present tariff being inadequate to service its debt obligations.
  • NIIF Infrastructure Finance Ltd. (“NIIF”) had threatened to cancel the balance sanctioned loan facility of Rs. 81 Crores if Amplus does not get an economic tariff.
  • Amplus was compelled to suffer revenue losses of over Rs. 51.71 Crores till 30.06.2024.

To seek emergent disposal, Amplus restricted its claim on issues of Capital Cost only, giving up claims re. Interest on Term Loan and Working Capital, IDC, and O&M Expenses.

Hon’ble APTEL by Judgement dated 25.10.2024: –

  • Set aside the HERC Order with respect to failure to conduct prudence check reflected in the disallowance of the Capital Cost incurred on higher DC module when it factored higher CUF for supply to Discoms.
  • Remanded the matter to HERC to redetermine the feasible CUF corresponding to the Capital Cost of AC: DC module allowed.
  • Clarified that the issues regarding Interest on term loan and working capital, Interest During Construction and O&M expenses shall not be reconsidered.
  • In the interregnum, Amplus is allowed a tariff of Rs. 3.03 per Kwh from the date of HERC’s order till the matter is finally decided by HERC upon remand.

 

Our Disputes Team Comprised Joint Managing Partner – Amit Kapur, Partner – Rahul Kinra, Senior Associate – Aditya Ajay and Junior Associate – Sanjay Nair S.

Sidharth Sethi | Book Launch | Sarkar Specific Relief Act, 19/e | LexisNexis

JSA is happy to announce that ‘Sarkar Specific Relief Act’ (19/e, LexisNexis) by Mr. Sudipto Sarkar, Senior Advocate and JSA Partner, Sidharth Sethi was released at a gala event organized on 16 October 2024 at The Oberoi, New Delhi.

This celebrated work was released by Hon’ble Mr. Justice Surya Kant, Judge, Supreme Court of India in the distinguished presence of Hon’ble Mr. Justice K.V. Viswanathan, Judge, Supreme Court of India.

Former Judges of the Supreme Court and High Court, leading Senior Counsels, In-house Counsels, lawyers from national and international law firms also graced the occasion with their presence.

 

About the book

Law relating to ‘Specific Relief’ is a cornerstone of Indian civil law, addressing the remedies available to aggrieved parties in cases where contractual or civil obligations have not been fulfilled. In an era where contracts and legal agreements form the bedrock of commercial and personal relationships, understanding the nuances of this law cannot be overemphasized.  This book aims to provide a comprehensive analysis of the Specific Relief Act, blending theoretical insights with practical applications. This edition has been significantly overhauled and will serve as a valuable resource for law students, academicians, practicing lawyers, and judges, offering insights that are both intellectually enriching and practically useful.