If you are not happy with the results, please do another search

JSA successfully represented the generator before APTEL, wherein relinquishment of Long-Term Access rights without any liability was allowed, due to Force Majeure events faced by the Generator

In a significant ruling, the Appellate Tribunal for Electricity (“APTEL”) in the case of M/s Brahmani Thermal Power Private Limited v. Central Electricity Regulatory Commission held that Brahmani Thermal Power Pvt. Ltd. (“BTPPL”) was entitled to relinquish its Long-Term Access (“LTA”) without any liability, due to force majeure events. By doing so, APTEL set aside Ld. Central Electricity Regulatory Commission’s (“Ld. CERC”) findings, by emphasizing that the delay in land acquisition by the concerned State Government was a Force Majeure event beyond BTPPL’s control. APTEL returned these findings after considering Regulation 18 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters), 2009. Brief facts 1.

The Appellant – BTPPL formerly known as Navbharat Power Private Limited, planned to establish a 1050 MW (2×525 MW) coal-based thermal power plant in Odisha. For this, it executed a Memorandum of Understanding (“MoU”) with State Government of Odisha on 09.06.2006. Under the MoU, the State Government through its instrumentality, Odisha Industrial Infrastructure Development Corporation (“IDCO”), was to acquire 1200 acres of land and hand it over free from encumbrances to BTPPL for setting up the power plant. BTPPL thereafter executed a Bulk Power Transmission Agreement (“BPTA”) with Power Grid Corporation of India Limited (“PGCIL”) for Long-Term Access (LTA) to the transmission network on 07.06.2010. 2. The land was identified and the acquisition process commenced. After certain payments by BTPPL, the Government of Odisha issued Section 4(1) notification under the Land Acquisition Act on 06.11.2007, which was followed by Section 6(1) notifications on 29.11.2008 and 11.12.2008. BTPPL obtained clearances from various authorities in relation to the identified land, some even before the BPTA was executed. 3. On 30.07.2009, the Collector, Dhenkanal informed that the Project area of 546.98 hectares fell within the Ayacut area of Rengali Right Canal System (“RRCS”), which required the matter to be settled with the Water Resources Department. Thereafter, the Water Resources Department inter alia requested BTPPL to revise its requirement of land or relocate the project. BTPPL expressed its inability to relocate. 4. Meanwhile, the MoU expired on 31.12.2011 and was not extended by the State Government. BTPPL had submitted a proposal reducing the share of Ayacut land and requested IDCO to initiate land acquisition process.

BTPPL had also requested PGCIL to postpone the commercial operation date of the plant. 5. It was only on 16.07.2012 that the Department of Water Resources gave its in-principal acceptance to establishment of the plant in the Ayacut area of RRCS. BTPPL then wrote to the State Government of Odisha to seek resumption of the land acquisition process. It also sought extension of the MoU, but in vain. 6. Finally, BTPPL issued Force Majeure notice on 25.06.2013 and sought relinquishment of the LTA and return of the bank guarantee submitted by it. PGCL advised BTPPL to approach Ld. CERC. Accordingly, BTPPL filed Petition No. 317/MP/2013 before Ld. CERC claiming Force Majeure under the BPTA and seeking return of the bank guarantee. 7. On 12.04.2017, Ld. CERC rejected BTPPL’s claim of Force Majeure, ruling that the project was abandoned for commercial reasons and that Force Majeure under the BPTA only provided temporary relief, not an exit from obligations. Ld. CERC further held that BTPPL must pay relinquishment charges as per Regulation 18 of the Connectivity Regulations, 2009 and it was not entitled to a refund of the ₹36 crore Bank Guarantee. Issues framed The issue as framed by APTEL was whether the BPTA was frustrated on account of the Force Majeure events faced by BTPPL. Findings of APTEL Re. Clause 9 of BPTA extends to permanent Force Majeure events 1. Clause 9 of the BPTA is not limited to only temporary Force Majeure events. The use of word “practicable” in the last sentence of Clause 9 merely indicates that the agreement may be continued after the Force Majeure event ceases to exist if the affected party finds it practical so to do. To say that Clause 9 applies only in case of “temporary failure to carry out the Terms of the Contract” would tantamount to adding words to the written agreement, which is impermissible. 2. APTEL in its earlier Judgment dated 19.05.2020 in Appeal No. 266 of 2016 titled PEL Power Limited v. CERC & Anr. regarding an identical clause had held the same. There is no stay on PEL Power Judgment. The PEL Power Judgment was followed in Judgment dated 14.05.2024 titled Himachal Sorang Power Pvt. Ltd. V. CERC & Ors. 2024 SCC OnLine APTEL 13.

The Appeal filed by CTUIL against the Himachal Sorang Judgment has been dismissed by Hon’ble Supreme Court on 27.08.2024. Re. Force Majeure events prevented BTPPL from setting up the plant 3. Ld. CERC’s finding that the project was abandoned due to commercial reasons is entirely unreasoned. Practice of writing unreasoned and cryptic orders needs to be deprecated sternly. Though Ld. CERC’s Order could be set aside on the ground of it containing no reasons, the Appeal was heard finally considering that it has been pending adjudication for more than 7 years. 4. The main reasons due to which the project could not be executed were (i) failure on the part of the State Government to acquire land for project before expiry of the notifications issued under Sections 4(1) & 6(1) of the Land Acquisition Act and (ii) failure on the part of the State Government to extend/renew the MoU beyond 31.12.2011. Both these factors were undoubtedly beyond the control of BTPPL and therefore, constitute Force Majeure events contemplated under Clause 9 of the BPTA. 5. When the MoU dated 09.06.2006 clearly made it an obligation upon the State Government to acquire the land required for the project through IDCO and place it at the disposal of BTPPL free from any encumbrances, there was no reason or occasion for BTPPL to initiate land acquisition process. It is the State Government which has failed to fulfil its obligations under the MoU for which BTPPL cannot be held responsible. 6. Regulation 8 of the Connectivity Regulations, 2009 is only applicable in cases of voluntary relinquishment, without being affected by Force Majeure events. 7. As on 25.06.2013, when BTPPL issued Force Majeure notice, there was no stranded spare capacity in the lines in question, since no work began on these lines. This also rules out applicability of Regulation 18, which presupposes stranded capacity on account of relinquishment. 8. Therefore, Ld. CERC’s Order is set aside, and the Appeal is allowed. CTUIL is directed to return BTPPL’s bank guarantee within 2 weeks. Conclusion APTEL’s Judgment rightly recognizes Force Majeure conditions faced by the generator which prevented operationalization of the LTA under BPTA. It also respects the Force Majeure clause in the BPTA by not resorting to a pedantic interpretation of the clause to hold that it covers permanent Force Majeure events also. Furthermore, it upholds the Force Majeure clause of the BPTA even in light of Regulation 18 of the Connectivity Regulations, 2009, by expressly holding that there was no stranded capacity in the present matter.

The Dispute team was led by Partner, Abhishek Munot with support from Of Counsel, Malcolm Desai, and Senior Associate, Samikrith Rao.

LX International Corp. in its sale of 35% stake in POSCO-India Pune Processing Center

JSA advised LX International Corp. in its sale of 35% stake in POSCO-India Pune Processing Center Private Limited (IPPC). LX International is a global trading company that provides a full suite of services across the entire value chain ranging from trading to business development, investment to financing, and raw material supply to logistics. POSCO Group is a global steel giant. IPPC is involved in processing and distributing value-added steel products, including hot-rolled coils, cold-rolled coils, galvanised steel, and specialty steel products.

Our Corporate team comprised of Lead Partner, Anand Lakra, Partner, Niharika Mepani and Senior Associate, Jinay Shah.

Our Taxation team comprised of Partner Kumarmangalam Vijay and Suraj Shettyand Associate, Tejasvi Shukla.

Our Competition team comprised of Partner, Vaibhav Choukse & Ela Bali and Principal Associate Nripi Jolly.

Pre-series A fund raising by FluxGen.

JSA advised climate tech startup FluxGen in securing its Pre-Series A funding. FluxGen combats water wastage, by using its advanced AI and IoT systems.

The round was led by IAN Alpha Trust and also saw participation from Rainmatter Investments, Gameskraft Technologies Private Limited, LV Angel Fund and Force Venture Trust, along with existing investors Axilor Investment Trust and Arali Ventures Trust.

The deal was led by Partners, Gerald Manoharan and Manuel Jose, with support from Principal Associate, Manas Ingle.

Media Coverage – CNBC TV18

Amit Kapur | Powering India’s Future: Policy, Markets and Innovation for a Clean Grid

Our Joint Managing Partner, Amit Kapur, recently participated as a panellist at the prestigious Council on Energy, Environment and Water (CEEW) event, “Powering India’s Future: Policy, Markets, and Innovation for a Clean Grid.”

During this insightful event, Amit contributed his expertise to the critical panel discussion on “Redesigning Power Markets: Unlocking Investments in Clean Energy by Introducing New Products, Services, and Market Participants.”

Amit was joined by esteemed panellists, including Chintan Shah | Samir Chandra Saxena | Ann Josey | Shaurya Kaushal, and Karthik Ganesan, who moderated the panel. The discussion emphasised the critical need for innovative approaches to reshape our power markets and attract investments to drive the transition to clean energy. Amit’s perspectives on fostering innovation within power markets are essential as we strive towards a sustainable energy future.

During the event, Shri Ghanshyam Prasad, Chairperson of the Central Electricity Authority (CEA) under the Ministry of Power, expressed gratitude to Amit for his ongoing support and collaboration. He remarked humorously, “I used to disturb him (Amit) a lot during the policymaking, and he was one of the people who used to legally support me that okay go ahead anything happens in the legal aspect of it, I’ll try to take care of those aspects.”

Amit’s insights were invaluable, and we are proud to see him recognised for his contributions.

Such engagements foster knowledge sharing and contribute significantly to shaping policies that impact our industry. We look forward to continuing these important conversations and driving meaningful change in power markets.

We invite you to read the report covering the event to gain a deeper understanding of the other discussions. Please click here to read the report.

The event marked the launch of CEEW’s latest study on “How India can Meet its Rising Power Demand? Pathways to 2030”, please click here to read the study.

We extend our heartfelt thanks to CEEW for sharing the video and the report.

JSA represents Peabody Energy Corporation (“Peabody”) in successfully obtaining an unconditional approval from the Competition Commission of India (“CCI”) in relation to the acquisition of a portion of the assets and business of Anglo Ame

JSA acted as the sole and lead Indian counsel to Peabody (acting through its newly incorporated special purpose vehicles, i.e., Peabody MNG Pty Ltd and Peabody SMC Pty Ltd), in securing an unconditional approval from the CCI in relation to the acquisition of a portion of the assets and business of Anglo and its subsidiaries’ steel-making coal portfolio in Australia (“Proposed Transaction”).

The deal value for the Proposed Transaction was approx. USD 3.775 billion (approx. INR 31,389 crores).

The Proposed Transaction was approved by the CCI on 17 March 2025 in 17 days. It was one of the first deals notified to the CCI solely on account of breaching the deal value threshold which has recently been notified by the Ministry of Corporate Affairs.

The team from JSA comprised Nisha Kaur Uberoi, Partner & Chair – Competition Practice, with Partner – Pranav Satyam, Principal Associates – Rahat Dhawan and Anand Sree; Senior Associate – Kamal Sharma; and Associates – Naman Katyal and Meghaa G.

The Indian project finance aspects were led by Lead Infrastructure Partner – Vishnu Sudarsan with Partner – Kartikeya G.S., and Associate – Siddhant Thakkar.

Jones Day acted as international legal counsel for Peabody on this deal.

JSA secures unconditional CCI approval for ONGC NTPC Green Private Limited’s landmark acquisition of Ayana Renewable Power

JSA successfully represented ONGC NTPC Green Private Limited (ONGPL) in obtaining unconditional approval from the Competition Commission of India (CCI) for its 100% acquisition of Ayana Renewable Power Private Limited (ARPPL).

ARPPL is a leading renewable energy platform, with an enterprise value of INR 195 billion (USD 2.3 Billion). ONGPL is a 50:50 joint venture between ONGC Green Limited and NTPC Green Limited, the renewable energy verticals of ONGC Limited (ONGC) and NTPC Limited (NTPC).

The CCI granted its unconditional approval on March 11, 2025.  This landmark transaction stands as one of the largest deals in India’s renewable energy sector and marks a significant milestone for ONGPL, representing its first strategic acquisition since its inception in November 2024.

Our competition team comprised of Partners, Vaibhav Choukse and Ela Bali, Principal Associate, Nripi Jolly, Senior Associate, Aditi Khanna, Associate, Faiz Siddiqui & Junior Associate, Arundhati Rajput.

Media Coverage – BusinessLine.