If you are not happy with the results, please do another search

JSA successfully represented The Tata Power Company Limited before Hon’ble APTEL in upholding TPCL’s network rollout plan for its Mumbai parellel distribution area common to MCGM/ BEST

On 11.03.2026, Hon’ble Appellate Tribunal for Electricity (“Hon’ble APTEL”) passed its judgment upholding Ld. Maharashtra Electricity Regulatory Commission’s (“Ld. MERC”) Order approving phase-wise network development in the Island City of Mumbai with respect to the parallel licensed area between BEST and TPCL.

By the said Judgment, APTEL has upheld the phase wise development of distribution network. In particular, it was held that:

(a)  Requirement of pre-owning of distribution network has not been mandated in the Electricity Act to be eligible for the grant of a license for the distribution of electricity.

(b)  As per Section 42 of the Electricity Act, a distribution licensee is mandated to develop and maintain an efficient and economical distribution system within its area of supply, which would mean progressive expansion and improvement of the distribution system. This is not a one-time activity; instead, it means the licensee must continuously plan and invest in infrastructure to meet growing demand and ensure reliability.

(c)  Thus, upon the grant of a distribution license, the Licensee cannot be expected to develop the entire distribution network at one go; the network will be developed in phases, and no timeline for such development has been mandated in the Act.

(d)  Section 43 of the Act also acknowledges that in the course of providing supply to a new customer, there would be instances where extension of substation and/ or distribution network would be required, and the same can be provided as per timelines specified by the State Commission/ or upon such extension.

(e)  Thus, even for meeting the Universal Service Obligation, the State Commission has to specify a timeline based on the requirement for extending the network, if any. Thus, the phased development of the distribution network under distribution license over 7 years as permitted, cannot be said to be in contravention of the provisions of the Electricity Act, 2003.

Further, in specific regard to the parallel distribution licensee scenario qua TPCL and BEST in Mumbai, Hon’ble APTEL, amongst others, noted that the approach followed by the Impugned Order to lay out the network by TPCL is the optimal approach considering its cost-effectiveness and to avoid selective bias in the coverage of areas or consumers. Adopting such an approach will enable faster coverage of the broader consumer base and foster a competitive market structure in line with the objectives of the Electricity Act. The same is preferable to sporadic network extensions to consumers located far from existing CSS/DSS, which typically involve longer lead times.

The exercise undertaken by Ld. MERC was the first of its kind in India, where a detailed network rollout plan was approved, considering practical difficulties in laying the network, consumer interests, and competitive neutrality. APTEL’s judgment establishes the foundation for laying parallel networks in India and provides much-needed clarity on implementing competition in electricity distribution.

TPCL was represented and advised by JSA team consisting of Abhishek Munot, Lead Partner; Kunal Kaul, Partner and Samikrith Rao Puskuri, Senior Associate.

JSA successfully represents ABS Marine Services before the Supreme Court in a landmark judgment on the ambit and scope of clauses dealing with ‘excepted matters’ in arbitration and arbitrability of disputes

In a significant and landmark ruling concerning arbitration landscape in India, a bench comprising Hon’ble Mr. Justice J.B. Pardiwala and Hon’ble Mr. Justice K.V. Viswanathan of the Hon’ble Supreme Court of India (“Supreme Court”) has clarified and laid down several important principles, including those pertaining to the (i) ambit and scope of excepted matters; (ii) arbitrability of disputes; (iii) jurisdiction of arbitral tribunals to rule on their own jurisdiction; and (iv) grounds for interference with an arbitral award.

In this matter, JSA Advocates & Solicitors (JSA) successfully represented ABS Marine Services (“ABS Marine”) before the Supreme Court in challenging the judgment (“Impugned Judgment”) passed by a Division Bench of the Hon’ble High Court at Calcutta (Circuit Bench at Port Blair), which had, in turn, set aside an arbitral award (as also an Order passed under Section 34 of the Arbitration & Conciliation Act, 1996 (“Arbitration Act”) upholding that award). Setting aside the Impugned Judgment, the Supreme Court restored the award and held that (i) one party to a contract cannot be a judge of the other’s breach when liability is disputed; (ii) a clause which bars both courts and arbitration creates an impermissible vacuum in legal remedies; and (iii) in the name of excepted matters, one cannot exclude justice.

The relevant facts are set out below:

ABS Marine had entered into a ‘Manning Agreement’ with the Andaman and Nicobar Administration (“A&N Administration”) for manning 17 vessels; and was responsible for providing complement of officers on board the vessels at all times. One vessel viz., M.V. Long Island, when on its way to Campbell Bay from Mazahua, started drifting from its intended track owing to rough sea with winds and struck a submerged rock. At high tide, it refloated on its own and using its engines proceeded to be berthed at Campbell Bay. However, in the process, there was damage caused to the vessel. A&N Administration claimed that it was on account of ABS Marine’s manpower’s neglect and levied certain penalties under a ‘default’ clause of the Manning Agreement. The Manning Agreement also consisted of an arbitration clause.

ABS Marine invoked arbitration challenging unilateral recovery of the above penalties. Relying on the default clause and the restricted reference of disputes to arbitration, A&N Administration claimed that their decision on recovery of penalties was “final and unchallengeable” and raised an objection to arbitrability. The sole arbitrator (Late Justice SS Nijjar) rejected this objection, and, by an award dated 8 May 2017 (“Award”), allowed all claims of ABS Marine, setting aside the penalties.

When A&N Administration challenged the Award under Section 34 of the Arbitration Act, the challenge was rejected and the Award was upheld. However, in a further appeal under Section 37 of the Arbitration Act before the High Court, the Award was set aside on the ground that the default clause was restrictive and expressly barred arbitration. ABS Marine challenged the Impugned Judgment before the Supreme Court; and the Supreme Court has been pleased to set aside the Impugned Judgment restoring the Award.

The decision of the Supreme Court assumes significance for crystallising the following principles:

  1. Once a dispute is held to be arbitrable, matters of fact are within the domain of the arbitrator.
  2. Non-negotiable principles of Rule of Law are not alien to interpretation of contractual clauses, especially when the State and its instrumentalities are parties to the same.
  3. No party can act as a judge in its own cause, i.e., the question whether the other party has committed breach cannot be decided by the party alleging breach. Such question can only be decided by an adjudicatory forum, especially when disputed questions of fact exist.
  4. Whether there was a wilful act of omission or negligence on the part of the Manning Agent/ABS Marine or its manpower cannot be decided by A&N Administration itself – which is the party alleging the breach.
  5. When a clause speaks of A&N Administration’s decision being final, it can only be in those cases where the wilful action or negligence is not disputed and, in that scenario, when a quantification is done by the administrator. However, where wilful action or negligence is disputed, the administration cannot claim that it is within its ken to decide the aspect of liability also.
  6. When ‘wilful act of omission or neglect’ is disputed by the Manning Agent/ABS Marine, such a dispute is arbitrable and within the ambit of the arbitration clause.
  7. A clause in restraint of legal remedies strikes at the very heart of the fundamental legal maxim ‘Ubi jus ibi remedium’ i.e. there is no wrong without a remedy. Such clauses must not be interpreted in a manner that create an impermissible vacuum in legal remedies, violating Section 28 of the Indian Contract Act, 1872.
  8. A&N Administration’s assertion that a decision by the administration even on the liability cannot be called in question in any court of law or before the arbitrator is opposed to all cannons of rule of law.
  9. Discriminatory clauses should not be incorporated in contracts between a private party on the one hand and the State and its instrumentalities on the other, foreclosing even redress through courts of law. Matters may be ‘excepted’ from arbitration, for that is a well-recognized concept, but a vacuum in legal remedies cannot result. ‘Except’ matters one may but ‘Exclude’ justice, one cannot.

The matter was argued by Mr. Niranjan Reddy, Senior Advocate and Mr. Sidharth Sethi, Advocate. A&N Administration was represented by Mr. Vikramjit Banerjee, Ld. Additional Solicitor General.

This decision goes beyond a routine arbitration matter. It is a sharp re-affirmation that contractual drafting cannot override foundational rule-of-law principles. It further clarifies that State authorities cannot unilaterally determine breach of contract, and that arbitral autonomy and access to remedies cannot be contractually engineered out by foreclosing judicial scrutiny of such determinations

The JSA Disputes team comprised Sidharth Sethi, Lead Partner and Shivangi Pathak, Associate.